印度尼西亚中Aceh 地区建设项目的关键延误因素。

Critical delay factors for construction projects in Central Aceh District, Indonesia.

机构信息

Department of Civil Engineering, Universitas Syiah Kuala, Banda Aceh, 23111, Indonesia.

Department of Architecture and Planning, Universitas Syiah Kuala, Banda Aceh, 23111, Indonesia.

出版信息

F1000Res. 2022 Apr 29;11:474. doi: 10.12688/f1000research.110024.2. eCollection 2022.

Abstract

Construction development in Indonesia is growing rapidly, especially in Central Aceh District. Construction projects have distinctive characteristics and are very complex, so that risk events can have a serious impact on the viability of the project. Project delays can result in cost overruns and project losses. Therefore, it is necessary to identify the factors causing project delays.The purpose of this study was to (1) identify the risk factors that cause delays in construction projects and (2) determine those particular risk factors that have a greater influence on construction projects. The location of this research was Central Aceh District. The data in this study were primary data in the form of a questionnaire and secondary data obtained from the literature related to this particular type of research. Questionnaires were distributed to respondents, namely contractor companies located in the Central Aceh District. The questionnaires were distributed to determine respondents' opinions about the level of influence of risk factors causing project delays. We used a validity test, reliability test, and descriptive analysis for data processing. Based on the results of the study from 47 respondents, the "very high influence" category (Mode=5) for the tool malfunction factor, cost estimation inaccuracy, increased work costs, implementation of new technologies, details, accuracy and conformity to specifications that are not appropriate, worker quarrels, poor project planning and management, poor condition at locations and accessibility difficulty. Of the 80 risk factors that caused project delays, eight risk factors were found to have a very high influence on the implementation of construction projects in Central Aceh District. The results of this study provide knowledge to contractor companies about the delay factors that have the most influence on project implementation so that they are expected to be able to manage risks to avoid losses.

摘要

印度尼西亚的建筑开发正在迅速发展,尤其是在中Aceh 区。建筑项目具有独特的特点且非常复杂,因此风险事件可能对项目的可行性产生严重影响。项目延迟可能导致成本超支和项目损失。因此,有必要确定导致项目延迟的因素。本研究的目的是:(1)确定导致建筑项目延迟的风险因素;(2)确定对建筑项目有较大影响的特定风险因素。本研究的地点位于中 Aceh 区。本研究的数据为调查问卷形式的原始数据和与特定类型研究相关的文献中获得的二手数据。向位于中 Aceh 区的承包商公司的受访者分发了调查问卷,以确定受访者对导致项目延迟的风险因素影响程度的意见。我们使用了有效性测试、可靠性测试和描述性分析来处理数据。基于来自 47 名受访者的研究结果,工具故障因素、成本估算不准确、增加的工作成本、新技术的实施、不适当的细节、准确性和符合规格、工人争吵、项目规划和管理不善、地点条件差和进入困难等因素的类别为“影响非常大”(模式=5)。在导致项目延迟的 80 个风险因素中,有八个风险因素被发现对中 Aceh 区建筑项目的实施有非常大的影响。本研究的结果为承包商公司提供了关于对项目实施影响最大的延迟因素的知识,以期能够管理风险以避免损失。

https://cdn.ncbi.nlm.nih.gov/pmc/blobs/3009/9860370/6278a65d44b7/f1000research-11-138988-g0000.jpg

文献AI研究员

20分钟写一篇综述,助力文献阅读效率提升50倍。

立即体验

用中文搜PubMed

大模型驱动的PubMed中文搜索引擎

马上搜索

文档翻译

学术文献翻译模型,支持多种主流文档格式。

立即体验