Int J Environ Res Public Health. 2019 Jan 11;16(2):192. doi: 10.3390/ijerph16020192.
Housing adaptation is a rehabilitation intervention that removes environmental barriers to help older people accommodate changing needs and age in place. In the UK, funding application for home adaptations to local authorities is subject to several procedural steps, including referral, allocation, assessment, funding and installation. The five stages need to complete in a sequential manner, often cause long delays. This study aims to investigate the timelines across these key stages of the adaptation process and examine the main causes of delays in current practice. A mixed-methods research strategy was employed. A questionnaire survey was first undertaken with all 378 local authorities in England, Scotland and Wales; it was followed by 5 semi-structured interviews and 1 focus group meeting with selected service providers, and 2 case studies of service users. The results showed that the average length of time taken to complete the whole process is relatively long, with the longest waiting time being observed at the funding decision stage. Delays were found in each of the key stages. Main causes of delay include insufficient resources, lack of joint work, legal requirements, shortage of competent contractors and the client's decisions. These issues need to be addressed in order to improve the efficiency and effectiveness of future housing adaptation practice.
住房改造是一种康复干预措施,它可以消除环境障碍,帮助老年人适应不断变化的需求和年龄,实现原地养老。在英国,向地方当局申请住房改造需要经过几个程序步骤,包括转介、分配、评估、资金和安装。这五个阶段需要按顺序完成,通常会导致很长的延迟。本研究旨在调查适应过程关键阶段的时间表,并研究当前实践中延迟的主要原因。采用混合方法研究策略。首先对英格兰、苏格兰和威尔士的所有 378 个地方当局进行了问卷调查;随后对选定的服务提供商进行了 5 次半结构化访谈和 1 次焦点小组会议,并对 2 名服务用户进行了案例研究。结果表明,完成整个过程所需的平均时间相对较长,最长的等待时间出现在资金决策阶段。在每个关键阶段都发现了延误。延误的主要原因包括资源不足、缺乏联合工作、法律要求、合格承包商短缺以及客户的决策。为了提高未来住房改造实践的效率和效果,需要解决这些问题。