Truong A, Tessler M J, Kleiman S J, Bensimon M
Department of Anaesthesia, SMBD-Jewish General Hospital, Montréal Québec.
Can J Anaesth. 1996 Dec;43(12):1233-6. doi: 10.1007/BF03013431.
This study was undertaken to determine if late starts of first cases in the Operating theatres at the SMBD-Jewish General Hospital remained a problem after identification of the causes of late starts and remedial actions being taken.
Hospital approval was obtained. A retrospective chart audit analyzed a two week period (10 days with 90 elective surgical cases) in October 1993. The time of entry by the first patient into each Operating Room (OR) was transcribed from the nursing records from each OR. A late start was defined as patient entry into the OR after 0745 hr. This audit revealed 77.8% of patients scheduled' for surgery at 0745 entered the OR late with a cumulative time lost of 1101 min. The reasons for this inefficiency were identified by a follow-up assessment in April 1995 as a result of this audit. Corrective measures included presentation of inpatients for the first case, reorganization of transport personnel schedules to facilitate arrival of patients to the OR, alteration of patient verification procedures prior to entry to the OR, and education of nursing, anaesthesia, and surgical personnel of the scope of the problem of late OR starts. All attending surgeons were notified either by letter or by discussion at departmental rounds. These measures were in effect by July 1995. A second audit, using the same methodology as the first, evaluated a two week period (10 days with 87 elective surgical cases) in October 1995.
The second audit showed 65.5% of patients (average of 9 operating rooms daily) scheduled for surgery at 0745 entered the OR late with 601 min lost. The average delay for late starting cases decreased from 15.73 +/- 4.56 to 10.54 +/- 3.92 min (P < 0.05).
Late OR starts are common and only modest improvements can be achieved without cooperation from anaesthetists and surgeons to arrive on time.
本研究旨在确定在查明SMBD-犹太总医院手术室首例手术延迟开始的原因并采取补救措施后,这一问题是否仍然存在。
获得了医院批准。一项回顾性病历审核分析了1993年10月的两周时间(10天,共90例择期手术病例)。从每个手术室的护理记录中抄录第一名患者进入每个手术室(OR)的时间。手术延迟开始定义为患者在0745时之后进入手术室。此次审核显示,安排在0745时进行手术的患者中有77.8%进入手术室延迟,累计损失时间1101分钟。1995年4月,由于此次审核进行了后续评估,确定了效率低下的原因。纠正措施包括将住院患者作为首例手术对象、重新安排运输人员时间表以方便患者抵达手术室、改变患者进入手术室前的核查程序,以及对护理、麻醉和手术人员进行手术室手术延迟开始问题范围的教育。所有主刀外科医生均通过信件或在科室查房时进行讨论的方式得到通知。这些措施于1995年7月生效。第二次审核采用与第一次相同的方法,评估了1995年10月的两周时间(10天,共87例择期手术病例)。
第二次审核显示,安排在0745时进行手术的患者中有65.5%(平均每天9个手术室)进入手术室延迟,损失时间601分钟。延迟开始病例的平均延迟时间从15.73±4.56分钟降至10.54±3.92分钟(P<0.05)。
手术室手术延迟开始情况常见,若没有麻醉师和外科医生按时到场的配合,只能取得适度改善。