Al Hudhaif Abdullah
Faculty of Economics and Administration, King Abdulaziz University, Jeddah, Saudi Arabia.
Int J Inf Technol. 2021;13(5):1943-1950. doi: 10.1007/s41870-020-00602-w. Epub 2021 Jan 20.
The purpose of this research is to examine the causes of delay in airport projects in general and the King Abdulaziz International Airport (KAIA) of Saudi Arabia in particular. The KAIA is the most strategic and busiest airport of Saudi Arabia, which transports millions of pilgrims from two hundred countries to perform Hajj and Umrah in Makkah. In general, more than 50% of construction projects fail on one more area. Our method of research is empirical based on the analysis of responses received from seventy-one respondents to our survey questions. We shall also synthesize literature that utilizes previous research and case studies on aviation and public project failures. We believe that this research will be valuable in ascertaining and mitigating direct causes for the numerous project delays in Kingdom of Saudi Arabia.
本研究的目的是考察机场项目普遍出现延误的原因,特别是沙特阿拉伯的阿卜杜勒阿齐兹国王国际机场(KAIA)。KAIA是沙特阿拉伯最具战略意义且最繁忙的机场,它将来自两百个国家的数百万朝圣者运送至麦加进行朝觐和副朝。总体而言,超过50%的建设项目在不止一个方面失败。我们的研究方法基于对71名受访者对我们调查问卷的回答进行分析,是实证性的。我们还将综合利用先前关于航空和公共项目失败的研究及案例分析的文献。我们相信,这项研究对于确定并缓解沙特阿拉伯众多项目延误的直接原因将具有重要价值。